How to connect the fiber when EPON system is used first time?
up-link1 and up-link2 are connected to Switch. The SC fiber port PON1 and PON2 are connected to PLC splitter via singlemode fiber, and the branch of PLC splitter will be connected to the fiber port of ONU. Up-link1 is relevant with PON1, and up-link2 with PON2, then it will work. Console port is for commissioning, and the RJ45 port is for WEB management.